Mimosa investigates a variance only when it exceeds 5 per cent of its budget. This month the variances were: sales price £6,000 favourable (budget £400,000), materials £4,500 adverse (budget £50,000), labour £2,100 adverse (budget £60,000) and overheads £1,800 adverse (budget £45,000). The variance to investigate is the:
- Amaterials variance
- Bsales price variance, as the largest in £
- Coverheads variance, as the nearest to 5 per cent without exceeding it
- Dlabour variance, as the largest of the factory costs in £
Each variance is compared with its own budget: sales 1.5 per cent, materials 9.0 per cent, labour 3.5 per cent and overheads 4.0 per cent; only materials exceeds 5 per cent.
Why each option is right or wrong.
- A (correct). Materials are 9.0 per cent of budget, the only variance above the 5 per cent limit.
- B. The sales price variance is the largest in £ but only 1.5 per cent of budget, within the limit.
- C. Overheads are 4.0 per cent of budget, within the limit; being near the limit does not trigger an investigation.
- D. Labour is 3.5 per cent of budget, within the limit, and materials are larger in £ than labour.
Reference: LO4.5 Management by exception; AAT L3 Management Accounting Techniques (MATS), Budgets and Variances.