A governance board is reviewing how an agile project will provide assurance without stage-gate sign-offs. How does agile governance mainly obtain assurance compared with stage-gate governance?
- AFrom transparent, working increments rather than document sign-off
- BFrom a single end-of-project sign-off once all the work is complete
- CFrom maximising documentation
- DFrom fixing scope in a contract
Agile governance obtains assurance from transparent, working increments rather than stage-gate document sign-off.
Why each option is right or wrong.
- A (correct). Agile governance draws assurance from working increments, not document gates.
- B. Agile governance is continuous, not end-only.
- C. Assurance comes from working evidence, not document volume.
- D. Assurance comes from working evidence, not a fixed contract.
Reference: AgilePM v3 Foundation syllabus, Governance, Compliance and the AgilePM Products (GV).