Confusion over who signs off a task versus who merely gives input is stalling a workstream. Which chart fixes this by naming, for every task, a single accountable owner plus responsible, consulted, and informed parties?
- Aan organization chart
- Ba RACI analysis
- Ca work breakdown structure
- Da project schedule
A RACI analysis names, per task, who is responsible, accountable, consulted, and informed, with a single accountable owner.
Why each option is right or wrong.
- B (correct). Naming one accountable owner plus responsible, consulted, and informed parties per task is a RACI analysis.
- A. An organization chart shows reporting lines, not the responsible, accountable, consulted, and informed roles per task.
- C. A work breakdown structure decomposes the work into tasks, not who is accountable, responsible, consulted, and informed for each.
- D. A project schedule sequences tasks over time, not who is accountable, responsible, consulted, and informed.
Reference: CTSC ECM v1.0 II.E.3.