On-hand balance is 20 units, the master production schedule adds 50 units, and 30 units are already committed to customer orders before the next MPS receipt. The available-to-promise (ATP) is:
- A70 units
- B40 units
- C100 units
- D20 units
Discrete ATP = on-hand + scheduled MPS receipt - orders committed before the next receipt = 20 + 50 - 30 = 40.
Why each option is right or wrong.
- B (correct). ATP = 20 + 50 - 30 = 40 units.
- A. This omits the committed orders.
- C. This adds all figures.
- D. This ignores the MPS receipt.
Reference: ASCM CPIM ECM IV.A Available-to-promise.