A planner must turn a firm master schedule for a pump into timed orders for its housings and seals. The logic that explodes those needs through the bill of material and lead-time offsets is:
- Arough-cut capacity planning
- Bmaterial requirements planning
- Csales and operations planning
- Ddistribution requirements planning
MRP takes the master schedule and, through the bill of material and lead-time offsets, generates timed component orders.
Why each option is right or wrong.
- B (correct). MRP explodes end-item needs into timed component orders via the BOM.
- A. Rough-cut planning checks resource load; it does not generate component orders.
- C. S&OP balances aggregate demand and supply, not component releases.
- D. DRP plans replenishment between distribution sites, not manufacture.
Reference: CSCP v5.0 ECM IV.A.2.