Planning, identification, control, status accounting and verification audit are the activities of which process?
- ACommunication management
- BRisk management
- CConfiguration management
- DBenefits management
Those five activities make up configuration management. Risk, benefits and communication management have different activities.
Why each option is right or wrong.
- C (correct). These five activities make up configuration management.
- A. Communication management handles engagement.
- B. Risk management handles uncertainty.
- D. Benefits management tracks benefits.
Reference: LO5.8 (configuration management activities); APM BoK 8th ed 5.11.3 Configuration management.