A newly installed process has passed installation qualification. The team now runs it across its specified operating ranges, including worst-case settings, to show it performs as intended. Which qualification is this?
- AInstallation qualification, confirming correct installation to the approved specification
- BOperational qualification, demonstrating the process operates as intended across its specified ranges
- CIncoming inspection, confirming purchased materials meet their specifications
- DDesign verification, confirming the design outputs meet the design inputs
Operational qualification challenges a process across its specified operating ranges, including worst-case conditions, to demonstrate it operates as intended, coming after installation qualification and before performance qualification confirms routine production. Running the process across its ranges is the OQ activity, which places this stage between IQ and PQ.
Why each option is right or wrong.
- B (correct). Operational qualification challenges the process across its specified operating ranges to show it operates as intended.
- A. Confirming correct installation to specification is installation qualification, the earlier stage already completed.
- C. Incoming material conformance is a receiving activity, not operational qualification.
- D. Design output versus input is design verification, not process qualification.
Reference: ASQ CQE BoK - III.D Verification and Validation.