Six weeks after implementing a permanent fix, a technician reviews records from the revised process and finds the original failure has not recurred. This activity is best described as:
- ADispositioning the nonconforming material
- BVerifying the effectiveness of the corrective action
- CContaining the problem on an interim basis
- DIdentifying and defining the problem
Verifying effectiveness confirms the implemented fix actually works and the failure no longer recurs, using evidence from the revised process running: records produced since the change and observation of the new method. It is the final step that truly closes a corrective action, distinct from containment, problem definition and disposition.
Why each option is right or wrong.
- B (correct). Checking the running process to confirm the failure no longer recurs is verifying effectiveness.
- A. Dispositioning material decides what to do with affected parts, not confirming the fix works.
- C. Interim containment happens during investigation, not weeks after the permanent fix.
- D. Identifying the problem is the first step, not this later confirmation.
Reference: ASQ CQT BoK 2024 - VI.B Corrective Action.