Gairloch Freight, a £900m firm, uses one operator across sea and road under a single bill of lading and asks what breaks down if a mid-journey leg is delayed. Which evaluation is most defensible?
- ANo one is accountable, because a bill of lading transfers all responsibility to the customer.
- BThe delay cannot be managed because multimodal contracts forbid intervention.
- CThe single multimodal operator remains accountable for discharging the contract on time across every leg, including the delayed one.
- DEach carrier is independently responsible, so the firm must chase every separate contractor itself when a leg is delayed or goes missing.
Under multimodal the single operator remains accountable across every leg, including a delayed one; independent-carrier chasing is intermodal, and the other options misstate accountability.
Why each option is right or wrong.
- C (correct). Under multimodal one operator stays accountable end to end, even for a delayed leg, the most defensible view.
- A. The bill-of-lading holder is accountable; responsibility is not transferred to the customer.
- B. Multimodal operators manage timing across legs, including delays.
- D. That describes intermodal; under multimodal one operator is accountable for the whole journey.
Reference: CIPS L5M10, LO 1, AC 1.2.4: multimodal transportation.