Helmsley Consulting wants rival tenderers to price exactly the same measured work so bids compare like for like, and appoints a cost consultant to measure it. What is produced, and what does it enable?
- AA cost-reimbursable arrangement.
- BAn activity schedule of stage payments.
- CA bill of quantities, enabling every tenderer to price a common measured basis.
- DA target cost, which the consultant would instead agree privately and separately with each individual contractor rather than publishing one common measured schedule for all of them to price.
A cost consultant's measured schedule is a bill of quantities, giving all tenderers a common basis to price, unlike a target cost, cost-reimbursable or an activity schedule.
Why each option is right or wrong.
- C (correct). A cost consultant's measured schedule is a bill of quantities, giving tenderers a common basis.
- A. Cost-reimbursable sets no advance measured basis for comparable bids.
- B. An activity schedule triggers stage payments; it is not the common measured tender basis.
- D. A target cost is agreed per contract; a common measured schedule for all bidders is a bill of quantities.
Reference: CIPS L6M5, LO 1, AC 1.3.3: bills of quantity.