A data centre loses utility power for several seconds at a time, and each dip hard-reboots the servers before the standby generator starts. To ride through these brief gaps, the team should install a:
- Aan uninterruptible power supply (UPS)
- Ban additional diesel generator only
- Ca surge-suppression power strip
- Da second power distribution unit
Riding through brief power gaps until the generator starts requires a UPS, not a generator, strip or PDU.
Why each option is right or wrong.
- A (correct). A UPS supplies battery power instantly, covering the seconds before the generator starts and preventing reboots.
- B. Another generator still takes seconds to start and cannot cover the instantaneous gap.
- C. A surge strip protects against spikes but stores no energy for an outage.
- D. A PDU distributes power to racks but holds no backup energy.
Reference: ISACA CISA (2024 Job Practice), Domain 4: Information Systems Operations and Business Resilience