Two tickets arrive at once: the entire sales floor is offline and one user elsewhere also reports no access. Which is the most appropriate first action to isolate whether they share a cause?
- AReimage the affected computers at the same time to rule out a software cause
- BLower the wireless transmit power across the site
- CCheck whether both connect through the same upstream switch or uplink
- DReplace the patch cables and wall jacks across the sales floor first
Checking the shared upstream device tests for a common cause efficiently; mass recabling, reimaging and power changes are premature.
Why each option is right or wrong.
- C (correct). Checking the shared upstream device tests for a common cause efficiently.
- A. Reimaging is disruptive and does not test for a shared network cause.
- B. Power changes are premature.
- D. Replacing cabling is costly and speculative before checking whether the two reports share an upstream device.
Reference: CompTIA A+ Core 1 (220-1201) objective 5.5.