During execution, two team members disagree and the project manager helps them reach a solution that fully satisfies both parties' underlying interests. Which conflict-resolution mode is being used?
- AAvoiding
- BSmoothing
- CCollaboration
- DForcing
Seeking a win-win that satisfies both sides is collaboration; forcing imposes one view, avoiding withdraws, and smoothing plays down differences.
Why each option is right or wrong.
- C (correct). Seeking a win-win that satisfies both sides is collaboration.
- A. Declining to engage with the conflict is avoiding.
- B. Emphasising agreement to reduce tension is smoothing.
- D. Imposing a decision by authority is forcing.
Reference: CompTIA Project+ PK0-005 objective 2.4.