An organization plans a big-bang system cutover with no fallback. The GREATEST risk the practitioner should raise is that:
- Asome users need brief retraining
- Bdata migration may run for several hours
- Ca failure leaves no way back to the old system
- Da short performance dip can occur at go-live
A big-bang cutover with no fallback risks a failure leaving no way back to the old system.
Why each option is right or wrong.
- C (correct). A big-bang cutover with no fallback risks total failure with no recovery.
- A. Retraining is minor next to having no way back if the cutover fails.
- B. A long migration is a delay, not the loss of a fallback path.
- D. A brief dip is minor compared with no route back to the old system.
Reference: ISACA CRISC (2025 Job Practice), Domain 4: Technology and Security