With an upper specification limit of 100, a lower specification limit of 70, a mean of 90 and a standard deviation of 5, the Cpk is:
- A1.33
- B0.67
- C2.00
- D1.00
Cpk = min[(USL - mean), (mean - LSL)] / 3 sigma = 10 / 15 = 0.67; the mean sits closer to the USL.
Why each option is right or wrong.
- B (correct). Cpk = min[(100-90), (90-70)] / (3 x 5) = 10 / 15 = 0.67.
- A. This uses the non-binding side.
- C. This ignores the off-centring.
- D. This is Cp for a centred process.
Reference: IASSC Black Belt BoK 2.4 Process capability.