A project lead lists the deliverable as a measurable, sustained cut in defect rate verified by data. Which of these is the most important result a project should deliver?
- AA completed and signed-off project charter document
- BA quantified, sustained improvement in performance
- CA current-state process map
- DA trained project team
A Lean Six Sigma project's defining deliverable is a quantified, sustained improvement in performance, validated with data.
Why each option is right or wrong.
- B (correct). The defining deliverable is a measured, lasting performance gain.
- A. The charter is an input created early on, not the improvement the project delivers.
- C. A process map is a tool used along the way, not the deliverable.
- D. A trained team is a means to the improvement, not the deliverable itself.
Reference: IASSC Green Belt BoK 1.1.3 Deliverables of a Lean Six Sigma Project.