A team wants a single chart that shows arrivals, work in progress and completions over time to spot where items pile up. Which tool fits?
- AA responsibility assignment matrix
- BA stakeholder power/interest grid
- CA Kano model diagram
- DA cumulative flow diagram
A cumulative flow diagram visualises arrivals, work in progress and completions over time, exposing bottlenecks and growing WIP.
Why each option is right or wrong.
- D (correct). A cumulative flow diagram shows arrivals, WIP and completions, revealing pile-ups.
- A. A RACI matrix assigns responsibilities.
- B. A power/interest grid maps stakeholders.
- C. Kano classifies features.
Reference: PMI-ACP, Delivery: visualising flow.