Question 1 of 10III. Business Environment

Two options are on the table. Building in-house has a 60 percent chance of a 100,000 gain and a 40 percent chance of a 50,000 loss. Buying has a 90 percent chance of a 50,000 gain and a 10 percent chance of a 10,000 loss. Based on expected monetary value, which should you choose?

Question 2 of 10I. People

A stakeholder with high power and high interest in your project, who had been closely engaged, has suddenly gone quiet and stopped responding. What does this most likely signal, and what should you do?

Question 3 of 10II. Process

Scenario: A predictive infrastructure project reports at the end of month 6. The budget at completion is 600,000. A performance chart shows the planned value at 300,000, the earned value at 240,000, and the actual cost at 280,000 for the work done so far. Based on the scenario, the project is both over budget and behind schedule. What should you do?

Question 4 of 10II. Process

Scenario: You manage an adaptive project delivering a customer portal in two-week iterations. The team's velocity has fallen from 40 to 28 story points over the last three iterations. A burndown chart shows the current iteration tracking well above the ideal line with three days left. Midway through the iteration, a senior stakeholder asks you to add a high-priority compliance feature immediately. Based on the scenario, how should you handle the stakeholder's mid-iteration request for the compliance feature?

Question 5 of 10III. Business Environment

Consider two options. Option A has a 70 percent chance of a 100,000 gain and a 30 percent chance of a 40,000 loss. Option B has a 50 percent chance of a 90,000 gain and a 50 percent chance of a 10,000 loss. By expected monetary value, which is better?

Choose an answer for each question, then check all 5 at once.

5 more free questions

Unlock 5 more PMI PMP (Project Management Professional) questions

Add your email to see the rest now. We will also send you the free exam pack for PMI PMP (Project Management Professional) and a short exam-tips newsletter at the start of each month.

Ready for the full set?PMI PMP (Project Management Professional): 1,080 questions, every answer explained.
Enrol on Udemy →£11.99 / $12.99 with code GP1NOV2026

GradePath Learning is an independent education provider and is not affiliated with, endorsed by, or approved by the Project Management Institute. PMP, CAPM, PMI-ACP and PMBOK are trademarks of the Project Management Institute, used here only to identify the exam these practice tests prepare you for.