Question 1 of 103.2 Organizing

Depot Futures involves Brayford Construction under a design-and-build contract, Voltrix Fleet on a framework call-off, and the council's own property team on enabling works. The Project Manager has agreed with the Head of Procurement that all three will be paid on measured milestones, with a monthly joint performance review and one standard route for resolving disputes. He wants the board to approve this once, for the whole project, instead of negotiating it separately in each work package. Which product should record it, and why?

Question 2 of 103.1 Business case

Depot Futures' business case records three benefits: operating cost per tonne collected falling from £84 to £71 within a year of the second depot opening, fleet carbon cut by 620 tonnes a year measured by vehicle telematics, and a crew facilities survey score rising from 58 to 75. It also carries a £70,000 a year dis-benefit for longer rounds in the north of the borough. The Finance Director objects that only the first benefit is stated in money, and asks for the other two to be converted to pounds. Is the business case fit for purpose, and why?

Question 3 of 101.1 Principles

At the end of stage 2, Ashfield Engineering's revised quote raised Clearline's forecast capital cost from £3.1m to £3.6m, while the Head of Product Development confirmed the £4.2m annual revenue forecast still stands. The Project Manager updated the business case and put both figures in the end stage report. The project executive reviewed the position with the senior user and senior supplier, and the board minuted its decision to continue. Is this a good application of the 'ensure continued business justification' principle, and why?

Question 4 of 103.3 Plans

Thornbury Rail's Project Manager has written the project product description, built the product breakdown structure and written a product description for each product. The signalling team says no signalling unit can be commissioned until the cabling tests are signed off, and the track team says ballast must be laid before cabling starts. Neither dependency is recorded anywhere yet. A colleague proposes going straight to estimating effort for each product. What should the Project Manager do next in product-based planning?

Question 5 of 102. People

Aldermoor's Fleet Manager leads the vehicle and charger work package, which carries milestone payments to Voltrix Fleet reviewed monthly. He knows the vehicles thoroughly but has never managed a supplier contract and has told the Project Manager he is unsure how to handle payment milestones and variations. He wants to keep the role. Stage 4 begins in ten weeks. A commercial adviser from the Corporate Programme Office has two days a week free, and the next contract-management course starts in twelve weeks. Which response is best?

Choose an answer for each question, then check all 5 at once.

5 more free questions

Unlock 5 more PRINCE2 7 Practitioner questions

Add your email to see the rest now. We will also send you the free exam pack for PRINCE2 7 Practitioner and a short exam-tips newsletter at the start of each month.

Ready for the full set?PRINCE2 7 Practitioner: 420 questions, every answer explained.
Enrol on Udemy →£11.99 / $12.99 with code GP1NOV2026

GradePath Learning is an independent education provider and is not affiliated with, endorsed by, or approved by PeopleCert. PRINCE2 is a trademark of the PeopleCert group, used here only to identify the exam these practice tests prepare you for.