A proposal routes all item sizing through a central estimation office. What does the Guide indicate about sizing?
- AThe Product Owner should set the sizes
- BStakeholders should size their own requests
- CThe Developers who will do the work are responsible for sizing
- DA central office should standardize all of the sizing, enforcing one scale
The Developers who will do the work are responsible for sizing.
Why each option is right or wrong.
- C (correct). The Developers who will do the work size items.
- A. The PO does not set sizes.
- B. Stakeholders do not size items.
- D. A central office is not the Scrum answer.
Reference: 2020 Scrum Guide, Product Backlog.