Planning an engagement over business resilience, the auditor finds the business impact analysis was last updated three years ago, before major changes to the operation. How should the auditor evaluate relying on it?
- AAs fully reliable, since a business impact analysis, once completed, gives a lasting picture of what is critical, so it needs no update despite the major operational changes
- BAs reliable because it is long, since the length of the analysis is what shows it is still accurate
- CAs unreliable for current planning, since a BIA that predates major change may no longer reflect which processes are critical, so it is refreshed
- DAs outside the engagement, since the currency of a BIA is a management matter the auditor need not consider
A BIA that predates major change may no longer reflect which processes are critical, so relying on it for current planning is unreliable and it is refreshed - not trusted indefinitely, judged by length, or treated as outside the engagement.
Why each option is right or wrong.
- C (correct). A BIA predating major change may no longer identify the right critical processes, so it is refreshed before relying on it.
- A. A BIA needs updating after significant change; it is not reliable indefinitely.
- B. Length does not show a BIA is current or accurate.
- D. The currency of the BIA affects resilience planning and is within the engagement.
Reference: CIA Part 2, Section A.3 (business impact analysis; business resilience); Global Internal Audit Standards.